DL/T5210.3-2009电力建设施工质量验收及评价规程第3部分:汽轮发电机组(英文版)
上QQ阅读APP看本书,新人免费读10天
设备和账号都新为新人

4.10 HP and LP Heater Erection

Applicable scope:applicable to HP and LP heater erection,with the following inspection items:heater inspection,heater erection(refer to Table 4.3.35 ordinary heat exchanger erection).

4.10.1 HP and LP heater inspection and acceptance are given in Table 4.10.1.

Table 4.10.1 HP and LP heater inspection

img

4.10.2 Mandatory provision implementation inspection of HP heater inspection and erection,LP heater inspection and erection,gland condenser inspection and erection,ST hall drain flash tank erection and other heat exchanger erection subsection projects are given in Table 4.10.2.

Table 4.10.2 Mandatory provision implementation inspection table of(  )subsection project

img