GB51005-2014水泥工厂余热发电工程施工与质量验收规范(英文版)
上QQ阅读APP看本书,新人免费读10天
设备和账号都新为新人

2 Terms

2.0.1 non-water medium

The medium used in the thermodynamic cycle other than water.

2.0.2 protection cell

The facility that protects the boiler drum,header,valve,and gauge attachment from rain,wind and freeze,etc.

2.0.3 chute

The ash conveying facility at the ash bucket of waste heat boiler,dust separator and other ash-falling place which is connected to the conveying equipment.

2.0.4 dust precipitation chamber

The equipment used to separate and collect the dust particles in flue gas.

2.0.5 engineering design documentation

The documentation that includes construction drawings,equipment and material list and manual,construction instructions,standard drawing handbook,design alternation,etc.

2.0.6 equipment technical documentation

The documentation that includes drawings,specifications,samples,installation instructions,maintenance instructions,operation instructions,measure and analysis report,etc.,provided by suppliers of equipment,instrument,and material.

2.0.7 commissioning & delivery organization

The temporary command organization established in the startup and commissioning phase of the waste heat power station.