3.3 Procedure of Construction Quality Acceptance

3.3.1 Construction quality of inspection lot shall be examined by work teams of construction contractor and documented in construction quality acceptance records for inspection lots,and verified by the quality inspector of construction contractor,then these records shall be submitted to the supervising engineer(or the technical superintendent of owner)for acceptance.

3.3.2 Construction quality of item works shall be examined after the inspection lots included in item works are accepted.The quality inspector of construction contractor shall fill out construction quality acceptance records for item works,and then these records shall be submitted to the supervising engineer(or technical superintendent of owner)for acceptance.

3.3.3 Construction quality of sectional works shall be examined after the item works included in sectional works are accepted.The quality inspector of construction contractor shall fill out construction quality acceptance records for sectional works,and then these records shall be submitted to the chief supervising engineer(or the technical superintendent of owner)for acceptance.