4 Preparations for Construction

4.1 Technical Preparations

4.1.1 The following technical documents shall be available prior to installation.

a)Engineering design documents;

b)Product technical documents;

c)Technical agreement of the supply and relevant minutes of meetings;

d)Construction technical documents.

4.1.2 Product technical documents shall include at least the following data and information:

a)List of machine train unit and packing list of the machine;

b)Erection,operation and maintenance manuals;

c)Assembly drawing,parts drawing,general arrangement drawing and process instrumentation diagram for each system;

d)Quality certificates of pipes,fittings,fasteners,valves with the machine;

e)Qualification certificates of the machine and accessories;

f)Records for inspection and assembly of parts;

g)Expected performance curve;

h)Records for the mechanical running test of the expander in hot state;

i)Inspection reports for chemical compositions and mechanical performance of main components and parts;

j)Non-destructive examination(NDE)reports of main components and parts;

k)Report of dynamic balance test;

l)Spare part list;

m)Other technical documents.

4.1.3 The drawings shall be reviewed prior to the construction.

4.1.4 Construction Method Statement shall be developed by erector and reviewed and approved by the owner/supervisor.

4.1.5 Persons participating in the construction shall receive technical clarification.