GB50377-2006选矿机械设备工程安装验收规范(英文版)
上QQ阅读APP看本书,新人免费读10天
设备和账号都新为新人

4 Equipment and Material Approach

4.1 General Requirement

4.1.1 This chapter is applicable to equipment and material site acceptance for mineral processing equipment installation.

4.1.2 When handling and lifting the equipment,the lifting point shall be the position marked on the equipment or packing case,and protective measures shall be taken to avoid any damage to the equipment.

4.1.3 Before equipment installation,open-case inspection shall be performed and inspection records shall be made.The equipment shall be protected properly after it is unpacked,and shall be installed in time.

4.1.4 Materials transported to the site shall be piled orderly according to their specifications,and preventive measures shall be taken to avoid damages.