GB/T 50744-2011 轧机机械设备安装规范 (英文版)
上QQ阅读APP看本书,新人免费读10天
设备和账号都新为新人

3.2 Baseline and Benchmark Setting up

3.2.1 Before installation of equipment,layout for baseline and benchmark shall be drawn and prepared in accordance with equipment process layout and survey control network,so as to determine locations of center reference peg and benchmark.Permanent center reference pegs and benchmarks shall be buried for center line of main axis of continuous production line and main equipment.

3.2.2 Permanent center reference pegs and permanent benchmarks(Figure 3.2.2)shall be buried firmly and well protected.

img

Figure 3.2.2 Permanent center reference peg and permanent elevation benchmark sketch

1-Permanent center reference peg;2-Permanent benchmark

3.2.3 Baseline and benchmark survey for the entire equipment units shall be accomplished for one time.

3.2.4 Settlement observation point should be buried after inspection and handover of equipment foundation and start to observe.It is recommended that settlement should be observed at set intervals from 7 to 30 days and be drawn out its curve chart.